Project scope consists of roadway widening and resurfacing, curb and gutter, sidewalks, storm sewer, water main, intersection signalization, pedestrian signal improvements, street lighting, and parkway restoration. The project improvements include:

· Additional and improved turn lanes at Chestnut/Waukegan and Glenwood Waukegan intersections
· Sidewalk replacement
· Storm sewer extensions
· Modernized traffic and pedestrian signal installation
· Driveway closures and reconfiguration
· Pavement will be widened and resurfaced
· Street lighting replacement

Project Timeline
April 2013 – Start of Construction
November 2013 – End of Construction




Friday, May 16, 2014

This week Berger Excavating completed punch list work on the project consisting of minor storm sewer, sanitary sewer and water main items.  This also included leak detection of the new portions of water main.  During the next few weeks the Village of Glenview and IDOT will be on site conducting final walk through inspections of the project, the streetlights will be turned over to the Village for maintenance, and the traffic signals will be turned over to IDOT for maintenance.”

Friday, May 9, 2014


The past two weeks Berger Excavating and their subcontractors has been working on punch list work on the project.  This consisted of replacing signage that had been damaged during the winter, minor curb repairs, streetlight testing and  completing the final touches on sanitary, storm and water main related items.

Next week Berger Excavating is scheduled to complete the remaining punch list items.

Monday, April 21, 2014

Saturday (4/12/14) Berger Excavating was on site making the final sanitary sewer repair which could not be completed until the new traffic signals were operational and the temporary traffic signals had been removed.

Last week Berger Excavating was removing temporary sidewalk installed over the winter and starting to clean up the project.  The landscaping subcontractor was also on site completing the remaining sod and mulch.  Also, the concrete subcontractor was on site replacing damaged sidewalk and curb.

This week Berger Excavating is scheduled to begin punch list work, which they anticipate taking a couple of weeks.  Additionally, the electrical subcontractor is scheduling activation of the street lights with ComEd.

Wednesday, April 2, 2014

On 3/19/14 the electrical contractor returned to the site and began minor work on the traffic signals and street lights.  Due to freezing temperatures some of the equipment was still frozen below the surface.  The contractor installed the traffic signal posts and mast arms during the week of 3/19/14.

 

Last week the contractor was able to start pulling wire through the underground conduits for the traffic signals and installed the traffic signal heads. 

 

This week the contractor is continuing installation of street light and traffic signal wires.  Weather permitting they will start installing street lights late this week or early next week.


The new traffic signals are scheduled to be activated on April 7, 2014.

 

Upon completion of electrical work Berger Excavating will return to the site to complete the final sanitary sewer repair, the concrete contractor will complete the remaining minor concrete items and the landscaper will complete the topsoil and sodding.