Project scope consists of roadway widening and resurfacing, curb and gutter, sidewalks, storm sewer, water main, intersection signalization, pedestrian signal improvements, street lighting, and parkway restoration. The project improvements include:

· Additional and improved turn lanes at Chestnut/Waukegan and Glenwood Waukegan intersections
· Sidewalk replacement
· Storm sewer extensions
· Modernized traffic and pedestrian signal installation
· Driveway closures and reconfiguration
· Pavement will be widened and resurfaced
· Street lighting replacement

Project Timeline
April 2013 – Start of Construction
November 2013 – End of Construction




Wednesday, November 27, 2013


 
This week, the electrical subcontractor, Elmund & Nelson,  was onsite connecting underground conduits to streetlight foundations and installing streetlight foundations on the west side of Waukegan Rd. from Chestnut Ave. south to Woodlawn Ave.  Additionally, the signage subcontractor was onsite this week installing regulatory, information, and street signage.

Next week, the concrete subcontractor is scheduled to be installing concrete sidewalk in various locations that were previously gapped due to conflicts, these locations could not be installed last week due to cold temperatures.  The landscaping subcontractor is also scheduled to be onsite next week grading and installing topsoil on the east side of Waukegan Rd. 

The Village of Glenview has met with ComEd to coordinate the relocation of the large green utility box located on the east side of Waukegan Road south of Pleasant Lane.  ComEd will begin the design necessary to relocate the box. A construction schedule is yet to be determined.