Project scope consists of roadway widening and resurfacing, curb and gutter, sidewalks, storm sewer, water main, intersection signalization, pedestrian signal improvements, street lighting, and parkway restoration. The project improvements include:

· Additional and improved turn lanes at Chestnut/Waukegan and Glenwood Waukegan intersections
· Sidewalk replacement
· Storm sewer extensions
· Modernized traffic and pedestrian signal installation
· Driveway closures and reconfiguration
· Pavement will be widened and resurfaced
· Street lighting replacement

Project Timeline
April 2013 – Start of Construction
November 2013 – End of Construction




Friday, October 4, 2013

This week Berger Excavating began to prep for asphalt base course widening along the west side of Waukegan Rd. and south side Chestnut Ave.  Berger's concrete subcontractor was onsite this week completing curb and gutter for the roadway along the the south side of Chestnut Ave. and west side of Waukegan Rd.  The electrical subcontractor was also onsite this week installing conduit for street lighting and traffic signals.

Next week Berger Excavating is scheduled to continue to prep for asphalt base course widening, with the asphalt subcontractor scheduled to be onsite late next week or early the following week.  The concrete subcontractor is scheduled to continue installation of driveway curb, sidewalk and concrete driveway pavement.  The electrical subcontractor will also be onsite next week continuing conduit installation and beginning installation of traffic signal handholes.