Project scope consists of roadway widening and resurfacing, curb and gutter, sidewalks, storm sewer, water main, intersection signalization, pedestrian signal improvements, street lighting, and parkway restoration. The project improvements include:

· Additional and improved turn lanes at Chestnut/Waukegan and Glenwood Waukegan intersections
· Sidewalk replacement
· Storm sewer extensions
· Modernized traffic and pedestrian signal installation
· Driveway closures and reconfiguration
· Pavement will be widened and resurfaced
· Street lighting replacement

Project Timeline
April 2013 – Start of Construction
November 2013 – End of Construction




Friday, September 13, 2013

This week Berger Excavating completed all water main, sewer and storm sewer work with the exception of a few small repairs where conflicts other utilities exist.  The contractor also completed excavation and install the stone base along the south side of Chestnut Ave.  The concrete subcontractor was also onsite installing concrete curb, sidewalk and driveway pavement in various locations on the east side of Waukegan Rd., the north side of Jefferson Ave., and the south side of Chestnut Ave.

Next week Berger is scheduled to continue earth excavation for the road widening along the west side of Waukegan Rd.  Also, Berger's concrete subcontractor is scheduled to install concrete curb and driveway pavement on the south side of Chestnut Ave. and on the west side of Waukegan Rd.