Project scope consists of roadway widening and resurfacing, curb and gutter, sidewalks, storm sewer, water main, intersection signalization, pedestrian signal improvements, street lighting, and parkway restoration. The project improvements include:

· Additional and improved turn lanes at Chestnut/Waukegan and Glenwood Waukegan intersections
· Sidewalk replacement
· Storm sewer extensions
· Modernized traffic and pedestrian signal installation
· Driveway closures and reconfiguration
· Pavement will be widened and resurfaced
· Street lighting replacement

Project Timeline
April 2013 – Start of Construction
November 2013 – End of Construction




Friday, September 6, 2013

This week Berger Excavating completed water service connections on Chestnut Ave. and curb, sidewalk and driveway pavement removal on Waukegan Rd.  Berger also began storm sewer installation on the west side of Waukegan Rd.  Berger's concrete subcontractor, Berquist & Zimmerman, was also onsite installing curb and sidewalk on Jefferson Ave.

Next week Berger Excavating is scheduled to complete storm sewer on Waukegan Rd. Berger is also scheduled to complete excavation for the proposed curb along Chestnut Ave. and will begin excavation for proposed curb along Waukegan Rd.  Water main work at intersection of Waukegan and Jefferson is also scheduled.  Berquist & Zimmerman will finish the concrete curb and sidewalk at the driveway entrances on Jefferson Ave.