Project scope consists of roadway widening and resurfacing, curb and gutter, sidewalks, storm sewer, water main, intersection signalization, pedestrian signal improvements, street lighting, and parkway restoration. The project improvements include:

· Additional and improved turn lanes at Chestnut/Waukegan and Glenwood Waukegan intersections
· Sidewalk replacement
· Storm sewer extensions
· Modernized traffic and pedestrian signal installation
· Driveway closures and reconfiguration
· Pavement will be widened and resurfaced
· Street lighting replacement

Project Timeline
April 2013 – Start of Construction
November 2013 – End of Construction




Friday, August 30, 2013

This week Berger Excavating began excavation for road widening, installed storm sewer and chlorinated water main on Chestnut Ave.  Additionally, Berger Excavating began removal of curb, sidewalk and driveway pavement on the west side of Waukegan Rd.  Berger's concrete subcontractor was also onsite this week installing sidewalk from Woodlawn Ave. north to Chestnut Ave.

Early next week, Berger Excavating is scheduled to continue curb, sidewalk, and driveway pavement removal on the west side of Waukegan Rd. and water service installation on Chestnut Ave.  Later next week, Berger will begin storm sewer installation on the west side of Waukegan Rd.  Additionally, Berger's concrete subcontractor is scheduled to install curb and gutter on Jefferson Ave. mid to late next week.