Project scope consists of roadway widening and resurfacing, curb and gutter, sidewalks, storm sewer, water main, intersection signalization, pedestrian signal improvements, street lighting, and parkway restoration. The project improvements include:

· Additional and improved turn lanes at Chestnut/Waukegan and Glenwood Waukegan intersections
· Sidewalk replacement
· Storm sewer extensions
· Modernized traffic and pedestrian signal installation
· Driveway closures and reconfiguration
· Pavement will be widened and resurfaced
· Street lighting replacement

Project Timeline
April 2013 – Start of Construction
November 2013 – End of Construction




Friday, July 19, 2013

This week Berger Excavating removed the existing curb, sidewalk and driveway pavement and installed a portion of the storm sewer in the work zone along the east side of Waukegan Rd.  Additionally, Berger installed the gravel base on Jefferson Ave.  A subcontractor for Berger Excavating also installed curb and sidewalk on Jefferson Ave.

Next week, Berger Excavating is scheduled to continue earth excavation and storm sewer work along the east side of Waukegan Rd.  Berger's concrete subcontractor is scheduled to install the remaining curb on Jefferson Ave.  Additionally, Berger's paving crew is scheduled to be in late next week or early the following week to pave Jefferson Ave.

Also next week, Berger will begin construction of the east side of the intersection of Waukegan Rd an Chestnut Ave.  This will consist of earth excavation, gravel base installation, and curb installation next week.  This work is scheduled to last for 10 days (weather permitting) at which time there will be no access to the east side of the intersection.