Project scope consists of roadway widening and resurfacing, curb and gutter, sidewalks, storm sewer, water main, intersection signalization, pedestrian signal improvements, street lighting, and parkway restoration. The project improvements include:

· Additional and improved turn lanes at Chestnut/Waukegan and Glenwood Waukegan intersections
· Sidewalk replacement
· Storm sewer extensions
· Modernized traffic and pedestrian signal installation
· Driveway closures and reconfiguration
· Pavement will be widened and resurfaced
· Street lighting replacement

Project Timeline
April 2013 – Start of Construction
November 2013 – End of Construction




Friday, July 12, 2013

This week Berger Excavating installed storm sewer and completed excavation  on Jefferson Ave.  Additionally, Berger installed the aggregate base course on Jefferson Ave. in preparation for concrete curb and asphalt work.

Next week the concrete subcontractor is scheduled to begin concrete curb on Jefferson Ave.  After the curb on Jefferson Ave has been installed, the asphalt subcontractor Peter Baker will begin asphalt work late next week or the following week.  

Additionally next week Berger is scheduled to begin curb, sidewalk, and driveway removal on the east side of Waukegan Rd. from south of Ammer Rd. to Woodlawn Ave. this work will involve daily right lane closures on northbound Waukegan Rd.