Project scope consists of roadway widening and resurfacing, curb and gutter, sidewalks, storm sewer, water main, intersection signalization, pedestrian signal improvements, street lighting, and parkway restoration. The project improvements include:

· Additional and improved turn lanes at Chestnut/Waukegan and Glenwood Waukegan intersections
· Sidewalk replacement
· Storm sewer extensions
· Modernized traffic and pedestrian signal installation
· Driveway closures and reconfiguration
· Pavement will be widened and resurfaced
· Street lighting replacement

Project Timeline
April 2013 – Start of Construction
November 2013 – End of Construction




Friday, June 7, 2013

This week Berger Excavating began installing water main along Waukegan Rd south of Chestnut Ave.  Also, this week Berger began potholing for existing utilities along Waukegan Rd north of Chestnut Ave.

Next week Berger is scheduled to continue water main installation by directional drilling on Waukegan Rd at Chestnut Ave and north of Chestnut Ave.  

Additionally next week, the electrical subcontractor is scheduled to activate the temporary traffic signals at Waukegan Rd and Chestnut Ave and begin removal of existing traffic signal equipment.