Project scope consists of roadway widening and resurfacing, curb and gutter, sidewalks, storm sewer, water main, intersection signalization, pedestrian signal improvements, street lighting, and parkway restoration. The project improvements include:

· Additional and improved turn lanes at Chestnut/Waukegan and Glenwood Waukegan intersections
· Sidewalk replacement
· Storm sewer extensions
· Modernized traffic and pedestrian signal installation
· Driveway closures and reconfiguration
· Pavement will be widened and resurfaced
· Street lighting replacement

Project Timeline
April 2013 – Start of Construction
November 2013 – End of Construction




Monday, June 24, 2013

Last week Berger Excavating continued water main installation in various locations along Waukegan Road.  Daily lane closures are still being used to complete work in the parkways along Waukegan Road.

This week Berger is scheduled to continue work on water main in a few locations along Waukegan Road.  Berger Excavating is also scheduled to begin water main installation on Chestnut Avenue late next week.  Additionally, Berger is scheduled to begin road work associated with the Taco Bell driveways.