Project scope consists of roadway widening and resurfacing, curb and gutter, sidewalks, storm sewer, water main, intersection signalization, pedestrian signal improvements, street lighting, and parkway restoration. The project improvements include:

· Additional and improved turn lanes at Chestnut/Waukegan and Glenwood Waukegan intersections
· Sidewalk replacement
· Storm sewer extensions
· Modernized traffic and pedestrian signal installation
· Driveway closures and reconfiguration
· Pavement will be widened and resurfaced
· Street lighting replacement

Project Timeline
April 2013 – Start of Construction
November 2013 – End of Construction




Friday, May 10, 2013

Construction to begin next week.

Changeable message signs indicating proposed start of construction have been installed at the intersections of East Lake Ave. and Waukegan, Waukegan and Winnetka, Chestnut and Lehigh, and Chestnut and John's Drive.

Next week Berger Excavating is scheduled to begin mobilizing onsite and potholing for utilities.  Additionally, a subcontractor is scheduled to begin tree removal onsite.  The temporary traffic signals will not be installed until construction dictates they are needed.